ISO/IEC DIS 27007, Edition 4 (unpublished), Clause 6.4.4
Communicating during the audit
Communication during the audit is planned, not improvised.
Three layers on this page. 1. The 2020 guidance as published, which cites ISO 19011:2018 and ISO/IEC 27001:2013. 2. The current external references a 2026 audit may use: ISO 19011:2026 and ISO/IEC 27001:2022/Amd 1:2024. 3. The DIS, limited to what the public record proves; inference is labelled.
The 2020 guidance as published
This is the 2020 layer. It cites ISO 19011:2018 and ISO/IEC 27001:2013, as the 2020 edition did. It is not a statement of the DIS.
ISO 19011:2018, 6.4.4 is followed with nothing added: the team meets at intervals to share what it has found, judge progress and move work between members; the leader communicates progress, significant findings and concerns to the auditee and client; evidence of immediate and significant risk is reported without delay; and where the objectives become unattainable or the scope must change, the reasons are reported to the client and auditee.
Communication during the audit is planned, not improvised. The team agrees who speaks to whom, how often, in what language and through what channel, and how a serious issue is raised before the closing meeting.
The DIS layer: what the public record shows
The DIS foreword aligns the revision with ISO 19011:2026 and ISO/IEC 27001:2022/Amd 1:2024. The DIS body is not public in full; this is the alignment, not a quotation.
The public DIS record does not show a change to this clause. The clause number and title are unchanged.
Evidence an auditor asks for
- Audit conductRecords of interim communications and any scope changes
The questions an auditor will ask
The auditor will ask how a mid-audit concern reached the auditee and how the team kept the client informed without breaking confidentiality.
Three tests to run before the next audit
- Ask for records of interim communications and any scope changes and trace it to the clause it is meant to satisfy.
Common gaps
- A live security exposure found during the audit and reported only in the final report
- Scope narrowed during the audit without telling the client
Prepare before the next audit
Agree the communication route at the opening meeting: daily check-in, escalation contact, language and channel. Record the decisions.
Cross-references
Held ISO/IEC 27007:2020 requirement set. https://www.iso.org/standard/77802.html
Retrieved 2026-10-19. 43 substantive clause records, the scope and terms page, and 26 Annex A audit-guidance rows, read from the held 2020 edition and its translation, retrieved 2026-10-19. The 27th annex row is the new 6.3 row. Used for the requirement and evidence text in our own words. The licensed text is not reproduced.